MANUFACTURING PROJECT/AIRCRAFT DEVELOPMENT PROJECT
Project description
(a) Show the dependencies of the activities by completing the Predecessors column of Table 1.<br />
(b) Draw an activity-on-arrow (AoA) network diagram for the project, using node numberings 5, 10, 15, 20, etc.<br />
(c) Using the AoA diagram, carry out a critical path analysis and determine:<br />
• the earliest and latest event times,<br />
• the activity schedule times (earliest and latest starting times, earliest and latest finishing times, and total float) for each activity<br />
• the critical path and project completion time.<br />
(c) Using Excel, draw a Gannt chart for the project. Show the float for each activity and the critical path on the chart.<br />
(d) Discuss how the project manager would use the activity floats in controlling the execution of the project.<br />
(e) Draw the resource chart assuming that each activity requires one team, and carry out resource levelling as much as possible.
(a) Show the dependencies of the activities by completing the Predecessors column of Table 1.<br />
(b) Draw an activity-on-arrow (AoA) network diagram for the project, using node numberings 5, 10, 15, 20, etc.<br />
(c) Using the AoA diagram, carry out a critical path analysis and determine:<br />
• the earliest and latest event times,<br />
• the activity schedule times (earliest and latest starting times, earliest and latest finishing times, and total float) for each activity<br />
• the critical path and project completion time.<br />
(c) Using Excel, draw a Gannt chart for the project. Show the float for each activity and the critical path on the chart.<br />
(d) Discuss how the project manager would use the activity floats in controlling the execution of the project.<br />
(e) Draw the resource chart assuming that each activity requires one team, and carry out resource levelling as much as possible.