Qi (for Mi) =12 in Task 1
Qi (for Li )= 20 in Task 2
Qi (for Ei) = 14 in Task 3
Qi (for Li) = 10 in Task 4
Qi (for Ei) = 9 in Task 5
Qi (for Mi ) = 12 in Task 6
Qi(for Ei) = 6 in Task 7
Task
|
Li
|
Ei
|
Mi
|
Ti
|
|
1 | |||||
2
|
0
|
?
|
3
|
||
2 | |||||
?
|
2
|
5
|
5
|
||
3 | |||||
3
|
?
|
6
|
7
|
||
4 | |||||
?
|
3
|
7
|
5
|
||
5 | |||||
2
|
?
|
4
|
3
|
||
6 | |||||
1
|
3
|
?
|
2
|
||
7 | |||||
1
|
?
|
4
|
2
|
b) Assume that the wage rate is £15/hr .Calculate the manpower cost for the initial project. If the project has to be completed in 20 days, you have to make a decision on increasing/decreasing a labor power. What is the suggested labor power in that case? Compare and contrast your solution to construction situation in terms of the total labor cost required for the initial project.
c) If an initial account of £47500 is invested for material payments in a construction project with 5% additional costs per day, how long should the project last before it triples its expenses?
d) Use the data on the no. of workers required (Li) and the quantity of work for task i (Qi) in order to prepare the appropriate graph. Fit straight line to the data using least squares method. Using the equation of the line of the best fit, estimate the value of Qi if Li is 5. What would be the duration (in days) of the task in that case?
e) Effective judgments have been made in relation to the choice of the total labor cost required for the project in Question b).
f) Check the validity of your estimated law in Question d) using the Pearson Correlation Coefficient.
g) Comment critically on how good you expect the forecast of Qi calculated in
Question d) to be..Click here for more on this paper.......